· Lower Howards Creek Sanitary Sewer Improvements
The improvements are a Consent Decree project with a completion deadline of January 31, 2013. The project is expected to eliminate 13 recurring sanitary sewer overflows (SSOs) in the Lower Howards Creek Watershed and 13 of the documented 27 system-wide recurring SSOs. Palmer Engineering Company (PEC) is the Engineer of Record. The Lower Howards Creek Sanitary Sewer Improvements are separated into five individual construction contracts as listed below.
- Lower Howards Creek Wastewater Treatment Plant and Pump Station
The Contractor (Smith Contractors) continues work associated with the construction contract. The regularly scheduled progress meeting for the project is January 17, 2012. Work to-date includes all mass blasting on the site for both the WWTP & future WTP, specifically Influent Mag Meter Vault, Selector Tanks, Oxidation Ditches, Clarifiers 1, 2, 3 & 4, RAS/WAS Pump Station and Plant Drains Pump Station. Trench blasting has also been completed for most on-site process piping and the 24” plant effluent line. Boring & Jacking for 200+ feet of 36” effluent line is complete, along with Directional Drilling of the 24” effluent line nearing completion. 18” D.I. Influent force main has been installed from the pigging vault to the anaerobic selector basins & oxidation ditches. Oxidation ditch base slabs and walls are in place. The top slabs for the Oxidation ditches are currently being placed. Also in-place or complete are the building slab, steel structure & metal trusses for the Administration Building, Mag Meter Vault, Dewatering Building, Electrical Building, Clarifier No. 1 and the RAS/WAS Pump Station. Influent PS progress includes concrete slab placement, the majority of the concrete walls and reinforcing below grade. As of December 20, 2011 the LHC WWTP project is approximately 44% complete. The Owner and the Engineer continue to finalize recommendations for changes to the project that include modifications to the odor control system at the new WWTP and inclusion of a surge tank at the Influent Pump Station. These changes will impact the engineering contract and construction contract. Smith Contractors has provided the Engineer with a weather delay request per the contract documents for the months of January-April. The request totals 32 days for inclement weather. A change order for this project is expected to be on the January 19, 2012 agenda.
- Lower Howards Creek Force Main
The project was bid on Thursday, September 8, 2011. The apparent low bidder was Cleary Construction, Tompkinsville, Kentucky with a bid of $2,479,255.60. The engineer's estimate for the project was $2,897,922.00. Approval for encroachment along the right-of-way has been received in a letter from the Kentucky Transportation Cabinet (KTC) dated March 26, 2010. The force main size will be 24-inch and the pipe material will be PVC. Kentucky Division of Water (KDOW) approval has been received for construction of this project as well. Only two private property owner easements were required for construction of this project and both have been acquired. The project has a 12 month construction period. The contract was awarded by the Commission at the September 15, 2011 regular meeting. The pre-construction conference for this project was held on October 19, 2011 at which time all Agreement Forms including Notice of Award and Notice to Proceed were signed. The contractor has initiated construction of the pipeline and continues to complete road bores and install casing pipe associated with road crossings as part of the project.
- Lower Howards Creek Sanitary Sewer Interceptor
The project was awarded to Cleary Construction, Tompkinsville, Kentucky for $3,586,705.00 by the WMUC at the July 7, 2011 regular meeting. The ATA package has been approved by the KDOW. The preconstruction meeting was held Wednesday, August 11, 2011. The project scope includes installation of approximately 14,885 feet of 24” and 15” gravity sanitary sewer and appurtenances. The pipe material is a combination of PVC and fiberglass. All 28 easements for the project have been received. The Agreement forms and Notice to Proceed have been executed by the Owner and Contractor. Construction is well underway and work to date includes site clearing, trench blasting, pipe installation and boring and jacking at Highway 627. The contractor has installed pipe from the new Influent Pump Station to the crossing of Old Boonesboro Road near the Stoney Brook Pump Station. The work continues to progress well ahead of schedule.
- Vaught Court Outfall Sewer (Complete)
The Vaught Road Outfall Sewer project is complete and included 1,796 feet of 15” sanitary sewer, 12 feet of 12” sanitary sewer, 459 feet of 8” sanitary sewer, 300 feet of 6” sanitary sewer, 160 feet of 42” steel encasement pipe, 24 manholes, 16 – 6” PVC Cleanouts, and other related appurtenances. The project was accepted for ownership and perpetual maintenance at the October 7, 2010 WMUC meeting. The one-year warranty period begins with the date of acceptance. WMU’s landscape contractor completed work the week of October 11th. Bluegrass Area Development District is working to close out the financing issues associated with this project as it relates to ARRA. A review of the ARRA paperwork associated with this project was conducted by EPA Region 4 on Wednesday, May 18, 2011. A 2nd review of the ARRA paperwork was completed Monday, October 17, 2011.
- Hampton Manor Outfall Sewer
The project scope includes installation of approximately 5,225 feet of 24”, 18”, 15”, 12” and 8” gravity sanitary sewer and appurtenances. Project plans are complete and WMU staff is not actively pursuing easements negotiations with property owners in the project area. DOW approval has been received. The project will not be advertised for bid until all easements have been acquired. A public informational meeting for the Hampton Manor and Vaught Road Gravity Sewer Projects was held on September 10, 2009 at George Rogers Clark High School. This project will be the last project constructed as part of the Lower Howards Creek Sanitary Sewer Improvements. This project will be postponed to a later date pending positive impacts from the other Lower Howards Creek projects and review of scenarios detailed in the Hydraulic Sewer Model. This project was ranked the No. 1 project in the Bluegrass region based upon the project rankings from the Bluegrass Area Development District's recent 409 Council Meeting.