skip to Main Content
Customer Service: (859)744-5434     Solid Waste: (859)744-1170

The following data is for the month of September 2020.

  • Water treated during the month of September 2020 was 158,446,000 gallons.  Average day water treatment was 5.28 MGD; peak day was 5.56 MGD.  YTD water treated is 492,728,000 gallons; YTD average day is 5.35 MGD.  Average day demand for September 2020 was 88% of capacity; peak day demand was 93% of capacity.  Capacity is calculated based upon a plant capacity of 6.0 MGD.
  • During September 2020, 100% of the water treated was from the Kentucky River; 0% of the water treated was from the Reservoir.  (Cost per 1000 gallons treated is $1.08 and YTD is $1.15 thru August 2020 – data for September was not available at the time of this report).
Elevated Water Storage Tanks
Carroll E. Ecton Reservoir
Water Treatment Plant

 

Construction of the WTP at 7055 Boonesboro Road adjacent to the Lower Howards Creek Wastewater Treatment Plant was initiated on March 5, 2018.  This project was designed and coordinated in conjunction with the 24-inch Raw and Finished Water Main Project (completed) as well as the Raw Water Intake improvements project (completed).  The preliminary engineering work developed six (6) Technical Memorandums establishing direction for design of the new treatment facilities.  Bell Engineering is serving as the Engineer of Record.  WMU has plans to continue to utilize the Carroll Ecton Reservoir as a back-up/secondary water supply and construct a raw water transfer pumping station at the existing water treatment plant in accord with construction of the new water treatment plant facilities.  All official approval documentation from KDOW has been received.  A preconstruction meeting was held on January 24, 2018 and the official sale of bonds has been completed establishing the remaining financing of the project.  The first progress meeting and an official groundbreaking ceremony was held on March 15, 2018.  The next monthly progress meeting is scheduled for Thursday, October 15, 2020.  Contractor payments show approximately 91% paid out for work completed through Pay Request No. 30.  On October 3, 2019, the WMU Commission approved a reduction in project retainage from 10% to 5% until all closeout requirements are completed.  As of the end of August 2020 the contractor is approximately 88% complete with construction.  On February 20, 2020, the WMU Commission approved an extension of one hundred, ten (110) days to the completion date and include the addition of seven (7) general cost change items to the original contract in the amount of +$255,679.00.  The adjusted Contract Price with inclusion of Change Order #2 is $20,331,857.00.  On July 16, 2020 the WMU Commission approved Change Order No. 3 to extend the completion date by ninety (90) days resulting in a substantial completion date of August 13, 2020 and final completion date of September 12, 2020.

Water Plant
Water Plant
Schedule
  • Design completion – 6/30/17
  • Solicitation of Construction Bids – 7/19/17
  • Construction Bid Opening – 10/27/17
  • Construction Bid Award – 12/7/17
  • Authorization for City to Issue Bonds – 12/7/17
  • First Reading of Bond Ordinance – 12/19/1
  • Second Reading of Bond Ordinance – 1/2/18
  • Bond Sale – 2/1/18
  • Bond Closing – 2/15/18
  • Notice to Proceed – 3/5/18
  • Construction Begins – 3/5/18
  • Groundbreaking – 3/15/18
  • Contract Time Commencement Date – 3/5/20
  • Adjusted Substantial Completion w/ approval of C.O. #3 – 8/13/20
  • Adjusted Final Completion w/ approval of C.O. #3 – 9/12/20

Quisenberry Lane Water System Improvements

The project will be constructed in-house and will provide upgraded water service to ten (10) residences to address low pressure and water quality problems experienced in this area due to low flow conditions.  The project scope includes installation of approximately 648 feet of water line and will eliminate a dead-end line by tying it to the new 24” transmission main on KY-627.  Water Main Replacement funds will be the source of funds utilized for the work.  The budgeted amount for this work is approximately $81,000.00.

Lincoln Street Water and Sanitary Sewer  Line Replacements

This city of Winchester redevelopment project (CDBG) involves installation of approximately 790 feet of 6” ductile iron water line and 1,270 feet of 6” and 8” sanitary sewer along Lincoln Street.  The water and sewer line replacement work is part of a larger project that will replace failing infrastructure in this area.  Preliminary costs for water and sewer line work are projected at $200,000.  An exact customer count has not been determined since final use of the properties included in the project area remains undetermined.  Work is anticipated to be initiated during calendar year 2019 upon completion of the CDBG process.

Winchester Bypass (Veterans Memorial Parkway) Utility Relocations

This project involves relocation of existing water and sanitary sewer infrastructure along the Winchester Bypass (Veterans Memorial Parkway) corridor from KY89 to KY627.  Staff attended a meeting at Department of Highways (KDOT), District 7 offices on Thursday, March 3, 2016, 10:00 a.m.  The meeting was held to coordinate the relocation or adjustment of facilities owned and operated by those impacted by construction of the project.  WMU staff is currently working with KDOT officials to obtain approval for selection of an engineering firm to facilitate the design of the relocated water and sewer facilities in the area.  The WMU Commission will be required to approve an engineering work order as well.  Management received a letter on May 26, 2016 from KDOT informing all parties that work on the project had been suspended for at least the next twelve months.  No specific cause for the suspension of work was provided.

Fulton Road Water and Sewer Relocation

This project includes construction and relocation of approximately 307 linear feet of 12-inch PVC and 248 linear feet of 8-inch sanitary sewer and appurtenances as part of the Fulton Road Extension project (City project).  The work will be constructed as part of the final phase of the Fulton Road Extension project.  The Kentucky Division of Water approval letter and construction permit have been received.  The project has been redesigned to accommodate easement acquisition.  Staff has met with the design engineer to provide comments.  All expenses associated with the relocation work are being borne by others.

Elevated Pressure Zone #3

The proposed project involved construction of a booster pump station and associated piping and valves to create a fourth elevated pressure zone in lower pressure areas that include French Avenue, Sunset Heights and Colby Road.  While a precise project area has not been determined, work is expected to address low pressure experienced in these areas and improve customer service.  The cost of the work was anticipated to be approximately $422,000 based upon preliminary cost estimates.  Water SDC funds are the potential source of funds to be utilized for this work.  The Commission approved Work Order No. 1 with Banks Engineering at the regular meeting on December 17, 2015 in the amount of $13,760.00 to prepare a Technical Memorandum (TM) outlining recommendations and alternatives.  Banks presented the TM information to the WMU Commission on May 20, 2017.  Banks provided multiple alternatives and recommended that no additional work be implemented until after the new WTP is designed since a new Hydraulic Grade Line (HGL) will be established at that point.