| Project | Status | Completion Date | Cost to date | 
| New Water Treatment Plant | Construction | January 2021 | $19,982,300.00 (as-bid) | 
| Oliver Street Water Line Replacement | Complete | September 2019 | $94,000 | 
| Quisenberry Lane Water System Improvements | Construction | November 2020 | $81,000 | 
| Lincoln Street Water and Sanitary Sewer Line Replacements (City) | Construction | Unknown | $200,000 (water and sewer only) | 
| Veterans Memorial Parkway Utility Relocations | Design | N/A | N/A | 
| Project 1107 Water Main Relocation | Complete | April 2019 | $14,042.79 reimbursed by GCF | 
| Fulton Road Sewer Line Relocation | Design (City project) | N/A | N/A | 
| Elevated Pressure Zone #3 | Preliminary Design | N/A | $422,000.00 (estimate) | 
| Flanagan/Madison Street Sanitary Sewer Improvements | Design | 12-31-23 (CD deadline) | $6,200,000 | 
| Strodes Creek Solids Facilities Improvements | Construction | January 2021 | $3,473,480.00 | 
| North Bloomfield Water Service Upgrades | Complete | December 2018 | $26,998.45 | 
| Woodland Drive Water Improvements | Complete | October 15, 2018 | $52,210.21 | 
| Hampton Manor Sanitary Sewer Improvements | Complete | April 19, 2018 | $1,288,128.00 | 
| Rowland Avenue Sewer Improvements | Complete | May 2018 | $36,351.98 | 
| Sylvania Ave. Water Line Replacement | Complete | May 2020 | $130,000 | 